METHOD STATEMENT FOR HYDROSTATIC TEST DURING WINTER SEASON

2016-12-29 15:04:06祁迎春
環球市場信息導報 2016年25期
關鍵詞:關鍵點注意事項案例

◎祁迎春

METHOD STATEMENT FOR HYDROSTATIC TEST DURING WINTER SEASON

◎祁迎春

隨著“走出去”“走進去”國家戰略的實施,眾多的國內電建公司承接到國外電站項目,尤其是‘一帶一路’上的優質項目。本文以哈薩克斯坦冬季高寒地帶進行的水壓試驗為實際案例進行注意事項的論述以及關鍵點的安排,為類似的項目執行提供參考。

As more and more Chinese companies have signed and will execute the power plant projects overseas, it is very challenging to perform the work especially to have the hydraulic test in winter Season of rough area, this paper illustrate the typical example successfully demonstrated in this case.

1.Scope of Hydro-Test

The average temperature in China north areas during Winter season is relative lower than other areas, where the lowest temperature in record is -38℃ in the most rough days, therefore,there must be special measures to prepare and execute to control work quality and safety as well as to protect the boiler system and equipment after Hydro-Test.

This method described as follows will introduce the general measures and solution to conduct Hydro-Test in winter season, which is normally applicable to the construction work to be executed in China north areas in Winter season.

2.Construction conditions

analysis

The prefabricated panel materials will be normally used for the boiler building and turbine house, while the indoor temperature is rather difficult to control due to the freezing cold weather and big heat emission from windows and doors even possible air leakage.

On the other hand, it shall be also necessary to consider and take considerate measures to prevent any freezing and corrosive occurrence after the Hydro-Test in the roughly cold days, which will impact the normal schedule of boiler operation due to the heavy working loads to keep insulation and top sealing after the test.

Conclusively, the Hydro-Test to be conducted according to the Project Schedule through winter season will create challenging risks in safety for boiler equipment and pipes, by contrary, the subsequent construction work even normal operation will be delayed in schedule if postpone the Hydro-Test.

3.Preparation works before HyDro-Test

3.1 General Working Procedures for Boiler Hydro Test

The overall Air Tight Test shall be arranged and conducted for the whole boiler hydro system to test and clear all the possible defects existing in welding seams, piping and sealing, whereafter the boiler equipment shall be insulated properly.

The heating surfaces in boiler top and sealing shall be insulated and executed finally after the Hydro-Test to discover the potential quality defect and remedy the defects prior to Hydro-Test.

3.2 Temperature Analysis and Heating Energy Calculation

According to the temperature records of these 3 months in last year of local area, the average temperature and lowest temperature could be calculated,and then calculated the indoor requested temperature and heating load comparing with requested temperature design pressure.

Based upon the calculation and analysis, it shall be confirmed to decide the necessity of installation of additional heating facilities to preventany freezing damages when the boilers are not operating neither considering the heating emission from equipment and process pipes, temporary heating estimation.

3.2.1 Light Tube Heaters will be additionally installed around ash silos, horizontal SH in end shafts and horizontal RH to improve and maintain the temperatures inside boiler.

3.2.2 Coke furnaces will be arranged in boiler building elevation 0m and will be put into use when the temperature falling down -20℃ or the indoor temperature is lower than 5℃.

3.3 Typical HSE Control Points

HSE team will coordinate with construction boiler team to have full and overall inspections of boiler parts and equipment, and conduct the safety training and explanation to all the team members attending the Hydro Test.

HSE team shall arrange appointed personnel to observe the weather condition and checkthe extreme cases in history record.

HSE team will make earlier preparation for counter measures to cope with any error or fault in boiler start-up or site blackout or personnel shifts changing.

3.4 Temporary Protective Measures

Based upon the analysis of local history weather record in local area and monitor the recent weather conditions on site, HSE team and boiler construction team will inspect the overall enclosing and capping conditions again in boiler buildings, such as main gates, windows & doors, flue ducts and air duct inlets, etc.

3.5 Ambient Temperature Observing Work

Observing points will be installed properly in boiler elevation 0m, 18m,57m, 62m to observe the ambient temperature prior to the normal activities of Hydro Test to select the most suitable time to start Hydro Test.

4.PROCESS CONCTROL DURING HYDRO-TEST

4.1 Scope of Hydro-Test

This preliminary system including feeding pipes, economizer, water wall, start-up system, SH and boiler drainage, sampling, air discharging,Nitrogen system.The Reheating Steam system including LTRH, HTRH and attemperator, drainage, air discharging pipes.

4.2 Environment Temperature Observation

According to boiler design, there are none down headers and water discharging in Platen superheater,secondary superheater and vertical reheater, so the water from Hydrotest could not be drained completely from such said areas, therefore, the temperature in tubes, furnace and flue ducts of such heating surfaces will be concentrating observation to control the temperature again any freezing, the temperature shall be more than 5 ℃.

During the preparation stage before test, the indoor temperature in Boiler Building shall be heated up, and HSE team will organize to carefully check every position for the possible air and steam leakage, and ensure that the indoor temperature could be increased gradually and maintained well in the temperature ranges as required, refer to the temperature Curve as follows:

4.3 Temperature Maintaining for Test Water

The temperature control for test water to be pumped to the boiler tubes is the key of overall hydro test.

The tubes of all heating surfaces shall be kept in the ranking of 21℃ -70℃, therefore, the test water shall be controlled in the range of 70℃ -80℃when pumping the feeding up to boiler during hydro test process.

The boiler will be water flushed to clean all the foreign items and subject to inspection and acceptance. Condensing water makeup tank will be pumped full of water, and start heating procedure to control the heating temperature less than 90℃, Meanwhile, chemicals ammonia and acetaldoxime will be injected in ratio to take the sampling mixture subject to test acceptance for its concentration. The condensing water pump will be started up to feed the water to boiler, adjusting the pump recycle opening to keep the desal water flow at the current of 70t/h,maintaining the water tanks operating in higher water level with accepted chemical concentration.

The boiler inside water shall be maintained warmly ranking 25℃ -45℃ for the sake of requirement from metal tubes and for the convenience of manpower inside inspection. The water will be drained utilizing the highest point of discharging valve in bulging system to exchange the hot desal water.

Boiler water in the whole bulging system shall be calculated every hour during the lower pressure stage according to Boiler Water Pressure Curve, then ensure that each part of heating surfaces shall be raised up 35℃-40℃ to satisfy all the tube walls in the bulging system be kept accepted temperature.

The coke furnaces shall be put into use to present any impact from the ambient environment when its temperature lower than 7℃ in boiler elevation 0m, which is very critical to maintain boiler ambient temperature higher than 5℃ and water in tubes are higher than 21℃.

5.Protective measure post Hydro-test

Proper and compete protection measure shall be taken after the Hydro Test considering the continuous freezing weather conditions in the job site until March, therefore, the feeding water to boiler shall be heated and kept recycling, minimum recycle 1 time when the environment temperature falling down -25℃ and control the boiler tube temperature no lower than 8℃, surely the water could be changed to present any freezing as per the tube conditions.

The quantity of coke furnaces could be adjusted according to the weather conditions outdoor and boiler enclosing conditions to keep the boiler indoor temperature over 0℃ after the Hydro Test.

(作者單位: 中國機械工業建設集團有限公司 )

猜你喜歡
關鍵點注意事項案例
聚焦金屬關鍵點
夏季使用農藥注意事項
今日農業(2021年12期)2021-11-28 15:49:26
肉兔育肥抓好七個關鍵點
今日農業(2021年8期)2021-11-28 05:07:50
案例4 奔跑吧,少年!
少先隊活動(2021年2期)2021-03-29 05:40:48
注意事項
請四大名著的作者吃飯,有哪些注意事項
學生天地(2019年35期)2019-08-25 08:58:12
隨機變量分布及統計案例拔高卷
發生在你我身邊的那些治超案例
中國公路(2017年7期)2017-07-24 13:56:38
說明文寫作注意事項
一個模擬案例引發的多重思考
中國衛生(2015年4期)2015-11-08 11:16:06
主站蜘蛛池模板: 亚洲中文字幕23页在线| 456亚洲人成高清在线| 国产精品亚洲片在线va| 波多野结衣无码AV在线| 四虎国产精品永久在线网址| 久久精品无码国产一区二区三区 | 国产精品乱偷免费视频| 狠狠ⅴ日韩v欧美v天堂| 中文字幕免费播放| 99在线观看国产| 蝴蝶伊人久久中文娱乐网| 国产精品极品美女自在线| 国产精品.com| 亚洲婷婷在线视频| 狠狠综合久久| 久久综合亚洲色一区二区三区| 四虎国产在线观看| 国产午夜人做人免费视频中文| 国产一区二区网站| 暴力调教一区二区三区| 5555国产在线观看| 国产chinese男男gay视频网| 国内精品91| 婷婷综合缴情亚洲五月伊| 97精品久久久大香线焦| 26uuu国产精品视频| 欧美日本在线播放| 国产乱子伦无码精品小说| 亚洲制服丝袜第一页| 国产高清在线观看| 91精品人妻互换| 久久免费视频6| 福利姬国产精品一区在线| 重口调教一区二区视频| 亚洲乱强伦| 久久影院一区二区h| 九九热在线视频| 精品久久久久久久久久久| 国产黄在线观看| 久久精品这里只有国产中文精品| 国产自视频| 直接黄91麻豆网站| 国产高潮视频在线观看| 精品国产美女福到在线不卡f| 亚洲成人免费看| 色综合热无码热国产| 九九久久99精品| 毛片一级在线| 国产网站黄| 岛国精品一区免费视频在线观看| 日本福利视频网站| 国产在线视频二区| 亚洲成A人V欧美综合| 国内精品一区二区在线观看 | 日韩欧美中文字幕在线韩免费| 午夜性刺激在线观看免费| 中文字幕va| 久久免费视频6| 国产在线拍偷自揄观看视频网站| 福利国产在线| 91成人在线免费视频| 国产办公室秘书无码精品| 国产a网站| 亚洲精品国产乱码不卡| 自慰网址在线观看| 秋霞一区二区三区| 狠狠色香婷婷久久亚洲精品| 无码国产伊人| 国产精品视频白浆免费视频| 91色国产在线| 国产女人18毛片水真多1| 伊人久久婷婷五月综合97色 | 久久国产精品国产自线拍| 91精品日韩人妻无码久久| 日韩毛片免费观看| 91久久精品国产| 欧美激情,国产精品| 国产精品林美惠子在线观看| 91av成人日本不卡三区| 欧美亚洲一区二区三区导航| Jizz国产色系免费| 97青青青国产在线播放|