楊林茂
在實(shí)踐鐵路建設(shè)項(xiàng)目質(zhì)量安全紅線管理以來(lái),工作中也不斷完善了一些做法,優(yōu)化了監(jiān)理實(shí)施細(xì)則和處理流程措施,部分問(wèn)題的整改(尤其是隧道缺陷整改)判識(shí)定性、過(guò)程盯控、過(guò)程記錄及影響資料留存、質(zhì)量驗(yàn)收等方面還存在一些問(wèn)題,結(jié)合工作實(shí)際,進(jìn)一步督促監(jiān)理人員落實(shí)質(zhì)量安全紅線管理職責(zé),落實(shí)問(wèn)題整改過(guò)程中的方案審查、整改盯控、檢驗(yàn)批驗(yàn)收、資料留存等方面的監(jiān)理責(zé)任,督促監(jiān)理人員充分發(fā)揮現(xiàn)場(chǎng)監(jiān)管作用,使質(zhì)量安全紅線管理工作上臺(tái)階。
鐵路建設(shè) ?質(zhì)量安全紅線 ??管理 ?思考
TU72??????????????
On the Practice and Thinking of Quality and Safety Management of Railway Construction Projects
Abstract: Since the implementation of the quality and safety red line management of railway construction projects, some practices have been continuously improved, and the supervision implementation rules and treatment process measures have been optimized. There are still some problems in the rectification of some problems (especially the rectification of tunnel defects), identification and characterization, process monitoring and control, process records and impact data retention, quality acceptance, etc. combined with the actual work, Further urge the supervisors to implement the quality and safety red line management responsibilities, implement the supervision responsibilities in the process of problem rectification, such as scheme review, rectification and control, inspection lot acceptance, data retention, etc., and urge the supervisors to give full play to the role of on-site supervision, so as to improve the quality and safety red line management.
Key Words: Railway construction; Quality and safety red line; Management; Thinking
為切實(shí)強(qiáng)化鐵路建設(shè)項(xiàng)目質(zhì)量安全意識(shí)和關(guān)鍵環(huán)節(jié)控制,實(shí)施鐵路建設(shè)項(xiàng)目質(zhì)量安全紅線管理,嚴(yán)肅查處質(zhì)量安全違規(guī)行為,中國(guó)鐵路總公司印發(fā)了《鐵路建設(shè)項(xiàng)目質(zhì)量安全紅線管理規(guī)定》(鐵總建設(shè)〔2017〕310號(hào))和《關(guān)于學(xué)習(xí)貫徹鐵路建設(shè)項(xiàng)目質(zhì)量安全紅線管理規(guī)定有關(guān)事項(xiàng)的通知》。結(jié)合新建中衛(wèi)至蘭州鐵路(甘肅段)監(jiān)理部貫徹鐵路建設(shè)項(xiàng)目質(zhì)量安全紅線管理情況,淺談鐵路建設(shè)項(xiàng)目質(zhì)量安全紅線管理的做法和思考。
為全面落實(shí)質(zhì)量安全紅線管理規(guī)定,為履行好監(jiān)理職責(zé)和完成好項(xiàng)目監(jiān)理工作,加強(qiáng)質(zhì)量安全紅線管理,根據(jù)委托監(jiān)理合同成立了監(jiān)理部,采取直線職能制,實(shí)行總監(jiān)理工程師負(fù)責(zé)制,認(rèn)真開(kāi)展質(zhì)量安全紅線管理自查自糾工作,質(zhì)量安全紅線問(wèn)題實(shí)行動(dòng)態(tài)管理并實(shí)行全過(guò)程控制。
1.1質(zhì)量安全紅線管理開(kāi)展方式
監(jiān)理部全體監(jiān)理人員簽訂質(zhì)量安全紅線管理承諾書(shū),明確質(zhì)量安全紅線管理的內(nèi)容與責(zé)任;總監(jiān)理工程師與建設(shè)單位、公司分別簽訂質(zhì)量安全紅線管理承諾書(shū)。并且監(jiān)理部每月制訂質(zhì)量安全紅線檢查計(jì)劃并聯(lián)合施工單位項(xiàng)目經(jīng)理部以“全員參與、全覆蓋、零死角”的原則,對(duì)現(xiàn)場(chǎng)和內(nèi)業(yè)全面開(kāi)展拉網(wǎng)式的質(zhì)量安全紅線管理自查自糾活動(dòng)。發(fā)現(xiàn)的問(wèn)題統(tǒng)一記錄,經(jīng)過(guò)分析,形成質(zhì)量安全紅線管理問(wèn)題庫(kù),督促整改。采取以下流程進(jìn)行質(zhì)量安全紅線問(wèn)題的管理。????質(zhì)量安全紅線問(wèn)題處理流程:發(fā)現(xiàn)問(wèn)題→準(zhǔn)確辨識(shí)質(zhì)量安全紅線問(wèn)題→制訂整改方案→問(wèn)題整改及監(jiān)控→責(zé)任單位自驗(yàn)→整改驗(yàn)收→質(zhì)量安全紅線問(wèn)題銷號(hào)。對(duì)質(zhì)量安全紅線問(wèn)題應(yīng)舉一反三,采取有效措施,避免同類問(wèn)題再次發(fā)生,實(shí)現(xiàn)質(zhì)量安全紅線管理“去存量、遏增量”的目的。
1.2質(zhì)量安全紅線管理開(kāi)展措施
監(jiān)理部質(zhì)量安全紅線管理經(jīng)過(guò)兩年多的落實(shí)和實(shí)踐,部分問(wèn)題的整改(尤其是隧道缺陷整改)判識(shí)定性、過(guò)程盯控、過(guò)程記錄及影像資料留存、質(zhì)量驗(yàn)收等方面還存在一些問(wèn)題,進(jìn)一步修改完善質(zhì)量安全紅線管理監(jiān)理實(shí)施細(xì)則和制度,完善措施。
1.2.1嚴(yán)格落實(shí)“五定”工作要求
監(jiān)理部總監(jiān)理工程師負(fù)責(zé)質(zhì)量安全紅線管理的統(tǒng)一部署,帶隊(duì)進(jìn)行紅線月度檢查,開(kāi)展對(duì)質(zhì)量安全紅線問(wèn)題的研究分析、定責(zé),負(fù)責(zé)質(zhì)量安全紅線檢查通報(bào)、報(bào)告的審核簽發(fā)。監(jiān)理部副總監(jiān)理工程師負(fù)責(zé)質(zhì)量安全紅線管理的日常管理,參加質(zhì)量安全紅線月度檢查,參加查處質(zhì)量安全紅線問(wèn)題的研究分析、定責(zé),參與質(zhì)量安全紅線檢查通報(bào)、報(bào)告的初步審核。監(jiān)理部質(zhì)量安全環(huán)保室負(fù)責(zé)質(zhì)量安全紅線管理檢查方案的制訂,組織開(kāi)展質(zhì)量安全紅線管理日常檢查并負(fù)責(zé)建立和管理質(zhì)量安全紅線問(wèn)題庫(kù),參加查處質(zhì)量安全紅線問(wèn)題研究的分析、定責(zé),編制質(zhì)量安全紅線檢查通報(bào)、報(bào)告。監(jiān)理部其他室和監(jiān)理組對(duì)質(zhì)量安全紅線管理及檢查負(fù)分管責(zé)任,參加質(zhì)量安全紅線月度檢查,參加查處質(zhì)量安全紅線問(wèn)題的研究分析、定責(zé),配合監(jiān)理部質(zhì)量安全環(huán)保室編制質(zhì)量安全紅線檢查通報(bào)、報(bào)告和問(wèn)題庫(kù)管理。
1.2.2嚴(yán)格落實(shí)“三統(tǒng)一”工作要求
(1)統(tǒng)一部署。聯(lián)合施工單位項(xiàng)目經(jīng)理部對(duì)每月質(zhì)量安全紅線管理自查自糾,采用現(xiàn)場(chǎng)實(shí)體排查和核查內(nèi)業(yè)資料相結(jié)合的方式全面開(kāi)展排查。
(2)統(tǒng)一檢查。監(jiān)理部定期聯(lián)合施工單位項(xiàng)目經(jīng)理部統(tǒng)一開(kāi)展專項(xiàng)檢查,開(kāi)展“全員參與、全覆蓋、零死角”拉網(wǎng)式檢查,檢查人員對(duì)存在的問(wèn)題需有詳細(xì)記錄并留存影像資料,檢查完畢后及時(shí)下發(fā)專項(xiàng)檢查通報(bào)并建立問(wèn)題庫(kù)、及時(shí)制定整治措施,及時(shí)落實(shí)整改實(shí)行閉環(huán)管理,發(fā)現(xiàn)的問(wèn)題統(tǒng)一記錄分析,形成質(zhì)量安全紅線管理問(wèn)題庫(kù),每月組織召開(kāi)分析總結(jié)專題會(huì)議,認(rèn)真分析出現(xiàn)的質(zhì)量安全紅線問(wèn)題原因并制定整改措施,舉一反三,狠抓落實(shí),全過(guò)程督促整。
1.2.3嚴(yán)格落實(shí)“一查處”工作要求
對(duì)質(zhì)量安全紅線檢查出的問(wèn)題及時(shí)召開(kāi)問(wèn)題分析會(huì),進(jìn)行研究、診斷、分析,按照職責(zé)、分工對(duì)責(zé)任人進(jìn)行嚴(yán)肅處理。針對(duì)工程實(shí)體質(zhì)量安全紅線問(wèn)題,視情節(jié)輕重,采取簽發(fā)監(jiān)理工程師通知單、召開(kāi)專題會(huì)或現(xiàn)場(chǎng)會(huì)、簽發(fā)工程暫停令、發(fā)函、約談、報(bào)告等措施,督促施工單位項(xiàng)目經(jīng)理部嚴(yán)肅處理。監(jiān)理部設(shè)立投訴舉報(bào)電話和聯(lián)系人,嚴(yán)肅查處舉報(bào)的質(zhì)量安全紅線問(wèn)題,舉報(bào)的質(zhì)量安全問(wèn)題經(jīng)查實(shí)的統(tǒng)一納入質(zhì)量安全紅線問(wèn)題庫(kù)。
要認(rèn)真執(zhí)行“五定、三統(tǒng)一、一查處”紅線管理制度,嚴(yán)格落實(shí)現(xiàn)場(chǎng)檢查責(zé)任和問(wèn)題整改銷號(hào)管理要求,進(jìn)一步規(guī)范質(zhì)量安全紅線檢查問(wèn)題庫(kù)的信息記錄及閉合管理,進(jìn)一步抓好問(wèn)題的整改銷號(hào),確保問(wèn)題整改閉合到位。進(jìn)一步落實(shí)監(jiān)理責(zé)任,做好監(jiān)理部及監(jiān)理人員的管理和檢查指導(dǎo),及時(shí)發(fā)現(xiàn)其工作中存在的問(wèn)題,及時(shí)督促整改。尤其是督促監(jiān)理人員落實(shí)質(zhì)量安全紅線管理職責(zé),督促監(jiān)理人員充分發(fā)揮現(xiàn)場(chǎng)監(jiān)管作用。以下是對(duì)質(zhì)量安全紅線管理的一些思考。
監(jiān)理部質(zhì)量目標(biāo)、安全目標(biāo)進(jìn)行細(xì)化,分解到各個(gè)監(jiān)理的工作階段、各個(gè)監(jiān)理的環(huán)節(jié)和每一個(gè)監(jiān)理人員,按照持續(xù)改進(jìn)和閉環(huán)管理的方式進(jìn)行監(jiān)管,實(shí)現(xiàn)每一項(xiàng)監(jiān)理工作、每一個(gè)監(jiān)理程序的標(biāo)準(zhǔn)化。專業(yè)監(jiān)理工程師按驗(yàn)標(biāo)要求的檢驗(yàn)項(xiàng)目、頻次、數(shù)量和方法逐一對(duì)標(biāo)檢驗(yàn),檢查合格的工程予以簽認(rèn)并準(zhǔn)許進(jìn)入下一道工序施工。有關(guān)驗(yàn)收內(nèi)容和實(shí)測(cè)數(shù)據(jù)應(yīng)記錄在個(gè)人《監(jiān)理日記》或?qū)S脵z查記錄中。工序質(zhì)量檢驗(yàn)不合格時(shí),專業(yè)監(jiān)理工程師應(yīng)立即指令施工單位項(xiàng)目經(jīng)理部整改并在《監(jiān)理日記》記錄相關(guān)問(wèn)題及整改情況,整改完成后重新檢驗(yàn)。為此,要加強(qiáng)以下方面的工作:一是進(jìn)一步細(xì)化質(zhì)量安全紅線問(wèn)題監(jiān)理預(yù)控(措施)要點(diǎn),堅(jiān)持和施工單位項(xiàng)目經(jīng)理部一道落實(shí)好隱蔽工程和關(guān)鍵部位作業(yè)實(shí)名制。二是規(guī)范監(jiān)理日記記錄內(nèi)容:包括工作時(shí)間、地點(diǎn)、涉及主要人員、工作內(nèi)容、發(fā)現(xiàn)的問(wèn)題及整改情況、陪同各級(jí)檢查情況等,總監(jiān)理工程師對(duì)副總監(jiān)理工程師、監(jiān)理組長(zhǎng)、各部門(mén)負(fù)責(zé)人的《監(jiān)理日記》每月檢查一次并簽署意見(jiàn),對(duì)其他監(jiān)理人員的《監(jiān)理日記》每月抽查一次且抽查人員不少于 10%并簽署意見(jiàn)。副總監(jiān)理工程師對(duì)監(jiān)理組長(zhǎng)和分管部門(mén)負(fù)責(zé)人的《監(jiān)理日記》每月檢查一次并簽署意見(jiàn),對(duì)其他分管監(jiān)理人員的《監(jiān)理日記》每月抽查一次且人員不少于 10%并簽署意見(jiàn)。監(jiān)理組長(zhǎng)(部門(mén)負(fù)責(zé)人)對(duì)本組(部門(mén))內(nèi)全部監(jiān)理人員的《監(jiān)理日記》每月檢查一次并簽署意見(jiàn)。專業(yè)監(jiān)理工程師對(duì)管轄范圍內(nèi)監(jiān)理員的《監(jiān)理日記》每?jī)芍軝z查一次并簽署意見(jiàn)。三是加強(qiáng)日常巡檢及旁站監(jiān)理工作,尤其是加大監(jiān)理部領(lǐng)導(dǎo)巡查力度。總監(jiān)理工程師所有在施工點(diǎn)每月覆蓋一次,副總監(jiān)理工程師負(fù)責(zé)范圍的所有在施工點(diǎn)每半月覆蓋一次 ,監(jiān)理組長(zhǎng)負(fù)責(zé)范圍的所有在施工點(diǎn)每周覆蓋一次,專業(yè)監(jiān)理工程師負(fù)責(zé)范圍的所有在施工點(diǎn)每?jī)商旄采w一次。旁站監(jiān)理人員旁站工作結(jié)束后,及時(shí)整理形成規(guī)范的《旁站記錄》,并將旁站部位和旁站記錄編號(hào)填入個(gè)人《監(jiān)理日記》和單位工程《監(jiān)理日志》中,滿足竣工資料歸檔要求。四是加強(qiáng)施工測(cè)量復(fù)核及抽檢工作,不定期地組織同施工單位項(xiàng)目部進(jìn)行聯(lián)測(cè)。
監(jiān)理部進(jìn)一步防范質(zhì)量安全紅線管理問(wèn)題的發(fā)生,按驗(yàn)標(biāo)要求組織檢驗(yàn)批、分項(xiàng)、分部工程質(zhì)量驗(yàn)收和單位工程質(zhì)量預(yù)驗(yàn)收,一是實(shí)測(cè)實(shí)量的項(xiàng)目,采用專業(yè)檢測(cè)工具或儀器設(shè)備進(jìn)行量測(cè),按驗(yàn)標(biāo)規(guī)定方法進(jìn)行計(jì)數(shù)、統(tǒng)計(jì)與評(píng)定。二是外觀或定性評(píng)價(jià)的項(xiàng)目,要采用目測(cè)、錘擊、破檢等方式進(jìn)行檢查并采用專業(yè)術(shù)語(yǔ)進(jìn)行定性描述,準(zhǔn)確表述質(zhì)量狀態(tài)。三是按照監(jiān)理規(guī)范要求,建立檢驗(yàn)批、分項(xiàng)、分部工程質(zhì)量驗(yàn)收一次報(bào)驗(yàn)合格情況臺(tái)賬,每月匯總統(tǒng)計(jì)當(dāng)月一次報(bào)驗(yàn)合格率,且在監(jiān)理月報(bào)中體現(xiàn)。檢驗(yàn)批、分項(xiàng)、分部工程驗(yàn)收不合格時(shí),簽發(fā)《監(jiān)理通知單》要求施工單位項(xiàng)目經(jīng)理部按驗(yàn)標(biāo)規(guī)定程序進(jìn)行整改,整改完成后重新驗(yàn)收。
依據(jù)合同、規(guī)范、標(biāo)準(zhǔn),按照公平、公正、獨(dú)立的原則開(kāi)展監(jiān)理工作。以現(xiàn)場(chǎng)監(jiān)理工作為核心,以監(jiān)理試驗(yàn)室為依托,加強(qiáng)對(duì)工地試驗(yàn)室的控制,做好原材料、構(gòu)配件、設(shè)備進(jìn)場(chǎng)的質(zhì)量檢驗(yàn)和驗(yàn)收工作。將監(jiān)理工作有針對(duì)性地進(jìn)行細(xì)化和分解,建立定人、定崗、定責(zé)、定點(diǎn)的檢查、驗(yàn)收制度;使檢查的內(nèi)容、檢查的方法、檢查的程序具體化、定量化并制定出質(zhì)量、安全控制要點(diǎn)。
以上是對(duì)“鐵路建設(shè)項(xiàng)目質(zhì)量安全紅線管理”的一些做法和思考。質(zhì)量安全紅線管理是通過(guò)上下齊動(dòng)使參建各方形成質(zhì)量安全管理合力;通過(guò)嚴(yán)肅查處質(zhì)量安全違規(guī)行為,以“零容忍”態(tài)度問(wèn)責(zé),形成質(zhì)量安全紅線“不敢違”的氛圍;通過(guò)設(shè)備工裝的不斷改進(jìn)、施工工藝的不斷完善、施工方法的不斷創(chuàng)新、質(zhì)量安全管理制度的不斷健全,技術(shù)措施和制度措施日益完善,形成“不能違”的環(huán)境;通過(guò)質(zhì)量安全紅線管理學(xué)習(xí)宣貫的不斷持續(xù),全員、全面、全過(guò)程檢查的不斷深入,參建各方人人知曉并自覺(jué)遵守質(zhì)量安全紅線規(guī)定,構(gòu)筑“不想違”的思想根基;通過(guò)自查自糾、整改閉合,達(dá)到工程質(zhì)量安全紅線問(wèn)題“去存量、遏增量”的目的。
參考文獻(xiàn)[1] 肖慧.淺談工地試驗(yàn)室在質(zhì)量安全紅線管理中的作用[J].建材發(fā)展導(dǎo)向,2019,17(4):65-66.
[2] 鄭楊.鐵路工程項(xiàng)目社會(huì)穩(wěn)定風(fēng)險(xiǎn)評(píng)估的問(wèn)題與對(duì)策研究[D].南昌:南昌大學(xué),2020.
[3] 趙子赫.鐵路建設(shè)項(xiàng)目成本管理系統(tǒng)的設(shè)計(jì)與實(shí)現(xiàn)[D].西安:西安電子科技大學(xué),2019.
[4] 劉卓高.鐵路施工工程路基質(zhì)量控制措施探究[J].中小企業(yè)管理與科技(中旬刊),2019(7):166-167.
[5] 王立志.海外鐵路RAMS實(shí)施方案的研究[J].機(jī)電信息,2019(17):173,175.
[6] 田勇.簡(jiǎn)談海外鐵路工程項(xiàng)目安全標(biāo)準(zhǔn)化管理的應(yīng)用[J].鐵路通信信號(hào)工程技術(shù),2020,17(1):115-118.
[7] 李惠玲,王婷,石秋紅.基于價(jià)值工程的限額設(shè)計(jì)方法在鐵路工程概算控制中的應(yīng)用研究[J].工程造價(jià)管理,2019(3):8-14.