聞檸永+尹貽林
摘要:隨著中國經濟的發展,許多國外的承發包模式也逐步引入進國內,在國內的環境下快速成長,如EPC總承包模式。EPC模式作為一種典型的工程總承包模式,EPC模式將工程項目設計-采購-施工和試運行工作交由工程總承包人完成。它具有建設周期長、施工情況復雜的特點,相較于DBB模式,EPC模式中承包人將承擔更多的工程風險。工程變更后引起合同價款調整,給業主或總承包商帶來利益受損,如何合理的規避這些問題是目前研究所欠缺的。本文的主要目標在于研究EPC模式下,工程變更引起的合同價款調整提供依據以及解決的辦法,為最終達到承發包雙方共贏的局面作出努力。
Abstract: With the development of China's economy, many foreign contracting modes are also gradually introduced into China and rapidly developed under the domestic environment, such as the EPC mode. As a typical project general contracting mode, in EPC mode, project design - procurement - construction and commissioning work is completed by the general contractor. It has the characteristics of long construction period and complex construction situation. Compared with DBB mode, contractors in EPC mode will take more engineering risks. The contract price adjustment caused by engineering changes brings the damage to the interests of the owners or general contractors. How to properly avoid these problems is currently lacking in the research. The main objective of this paper is to study the basis and solution to contract price adjustment caused by engineering change under the EPC mode and make efforts to finally achieve win-win situation for both parties.
關鍵詞:EPC模式;工程變更;合同價款調整
Key words: EPC mode;engineering change;contract price adjustment
中圖分類號:F284 文獻標識碼:A 文章編號:1006-4311(2018)08-0022-04
EPC模式的工程總承包是一些發達國家根據市場需求,一步步探索,逐漸演變發展起來的一種承發包模式,近年來受到普遍歡迎。在國外,理論界一直以來都將EPC模式作為設計-建造(DB模式)模式的一個分支,專門研究它的文獻很少[1]。1999年,國際咨詢工程師聯合會認識到這種模式與設計-建造模式的根本區別及其廣泛的應用前景,編寫了FIDIC《設計采購施工(EPC)/交鑰匙工程合同條件》,從而確定了該模式在工程承包模式體系中的獨立性地位。學者們對于EPC模式下的工程變更引起的合同價款調整的研究較少。99版FIDIC《設計采購施工(EPC)/交鑰匙工程合同條件》對工程變更的確定進行了部分的規定及研究,但是鮮見深入細致研究者,在本文在,討論了它的研究的意義,力求做到EPC業主與承包商共贏。……